About HESSI
 
MISSION STATUS:

On April 19 HESSI was moved to Bldg 1555 at VAFB - the Orbital Sciences facility where the spacecraft will be mated with the Pegasus rocket. The move went smoothly and the spacecraft is now in tests leading up to integration with the rocket. LAUNCH IS NOW SCHEDULED FOR JUNE 7,

HESSI is at Bldg 1555, VAFB

MAJOR HESSI EVENTS DURING 2001

April 2001 (VAFB):

  • Continuing Attitude Control System simulations and tests.
  • Continuing to practice flight operation procedures.
  • Moved spacecraft to Bldg 1555 at VAFB.

March 2001 (VAFB):

  • Completed setup of Hot Bench at UCB and performed Attitude Control System simulations and tests.
  • Moved spacecraft and GSE to Building 1610 on higher ground at VAFB to avoid power outages and flooding.
  • Completed 4 Day No Command test.
  • Practising flight operations procedures.

February 2001 (VAFB):

  • Attached solar panels and performed 1st Motion Test.
  • Repeated spacecraft and instrument functional tests.
  • Reviewed and tested flight operations procedures.
  • Presented mission status and readiness to PreShipment and Red Team Reviews.

January 2001 (JPL and VAFB):

  • Spacecraft returns to thermal vacuum for testing of cryocooler performance at 50W and amplifier trims. Thermal Vacuum successfully concluded on January 8.
  • Mass Properties Measurements and Spin Balance performed on January 9 and 10.
  • Spacecraft transported to VAFB on January 12.
  • Setup and Safe-to-Mate testing performed January 13-14.
  • Spacecraft functionals and calibrations successfully performed on Jan 15-17.

 

MAJOR HESSI EVENTS DURING 2000

December:

  • Solar array deployment in thermal vacuum successfully tested.
  • Endurance thermal-vacuum testing including hot and cold dwells and extended thermal balance testing.
  • Learned that spectrometer is colder than expected at planned cryocooler power level. Good news: we can operate with less power.
  • Observed hf noise on two detectors.
  • Made amplifier trims to correct noise problem.

November:

  • Spacecraft transported to JPL on November 1-2.
  • Preliminary setup and testing performed.
  • Solar Arrays attached and deployment tested.
  • Vibration testing of X , Y and Z axes successfully completed.
  • Separation/shock testing successfully completed.

October:

  • Flight battery reconditioned and installed.
  • Spacecraft fully functional and running.
  • Red Team and Pre-Environmental Reviews.

September:

  • Ran and passed the following spacecraft functional tests: command and data handling, inertia adjustment device, thermal, launch vehicle interface, electrical power system.

August:

  • The Spacecraft Electronics Module, Solid State Recorder, Sun Sensors and Magnetometer have been returned from subcontractors and re-installed on the spacecraft. All units checked out OK.
  • Requalified Transponder and RF Switch received and installed on the spacecraft.
  • Safe-to-Mate functional tests run for all components.

July:

  • Solid State Recorder, Transponder, RF Switch, Sun Sensors and Magnetometer all removed from the spacecraft and delivered to the subcontractors for retesting and qualification.
  • The Spacecraft Electronics Module completed testing at Spectrum Astro by the end of the month and checked out OK.

June:

  • New deck completed and installed.
  • Refurbished bus structure completed and aligned.
  • New imager support ring completed and installed.
  • Implementing several plans running in parallel to provide new spectrometer cryocooler.
  • New solar array substrates completed at COI.
  • Requests for Action received from May review team.  Spacecraft Electronics Module shipped back to Spectrum Astro.
  • GPMC authorizes new integration, test and launch plan on condition that cryocooler issue is resolved by September. New launch date set for March 2001.

May:

  • Spacecraft minus imager and spectrometer taken to Bell Labs for thermal test.  From May 2 to May 5 spacecraft undergoes 6 cycles between +45 and -20C.  Spacecraft passes all functional tests except for firing of frangibolts.  Problem is found to be a  broken wire which is fixed.  All other wiring is scrutinized and plans prepared for high pot and other testing.
  • Designed stronger imager support ring.
  • Decided to repair broken solar panels and also contract new panels to have two options and choose the best in future.
  • Honeycomb deck found to be slightly warped.  Began fabrication of new deck.
  • Spectrometer cryocooler found to have deteriorating performance since mishap.
  • Spectrometer cryocooler flight spare starts also exhibiting problems during burn-in tests.
  • Termination/Recovery Review held at UCB on May 15 and 16.
  • HESSI Test Mishap Investigation Board issues their report on May 18.
  • After the thermal test and fix of frangibolt wiring, spacecraft is powered up and running most days.
  • Flight operations team continues preparations,  including simulations of Launch and Early Orbit plus regular passes.

April:

  • Spacecraft carefully inspected and found to be in good shape with the following exceptions:  two damaged solar arrays,  broken imager support ring,  one strained cable.
  • Review meeting between GSFC and UCB held on April 4.  Recommendation is to do more inspection plus a thermal test.
  • Imager (which rests on the broken imager support ring) shipped to PSI so they can fully test and recalibrate.
  • Spectrometer removed and tested for leaks.  None found.

March:

  • Solar arrays integrated and thermal blankets installed.
  • Spacecraft shipped to JPL.
  • Pass EMC testing.
  • Pass random vibration testing.
  • Spacecraft over-vibrated in sine-burst test (20 G's applied instead of 2 G's for 200 milliseconds).
  • Review team gathered to investigate the over-test.
  • Spacecraft shipped back to UCB for inspection and evaluation.

 

January/February:

  • Spacecraft Bus delivered to UC Berkeley.
  • All instruments successfully integrated and tested at UCB's Spacecraft Integration Facility.
  • Pass Environmental Reviews.
  • Successful end-to-end testing of telemetry and commands between spacecraft and ground system via the 11 meter antenna.